Locke talks about 350 metric tonnes of concrete as being the largest concrete pour in Europe ever (apart from nuclear and military facilities). Concrete is calculated by volume. 350 tonnes is about 160 cubic metres - basically about enough to fill a room that is 9 metres long x 9 metres wide x 2 metres deep. The price of this concrete would be somewhere in the region of £10,000 at 2014 prices. Many projects exist where over 3,000 cubic metres has been poured in a day (about 6,600 tonnes), so 350 tonnes isn't something a decent sized company would get too excited about, and you could probably complete it in 3-4 hours with just one concrete pump.